Construction (8pm to 5am)
Summary of Total Works
Nearly 26 weeks closures out of 78 to 80 weeks total duration
Burpham Section Summary
London Road closed nearly 9 weeks out of 18 to 20 weeks, plus 4 weeks side road closures (to be confirmed)
Phase 0
4 weeks closure of Burpham Lane and New Inn Lane, will affect Aldi customers significantly.
Phase 1
10 nights total closure out of 4 weeks duration.
Phase 2
4 nights total closure out of 7 to 8 weeks duration
Phase 3
6 weeks northbound closure out of 7 to 8 weeks duration
Boxgrove Roundabout Summary
4- way traffic lights for 4 phases, with no closures, out of 21 weeks duration
Stoke Park/Guildford High School Section Summary
Nearly 17 weeks closure, out of 35 weeks duration
Phase 1
6 weeks total closure, incorporating 4 weeks Nightingale Road and Cross Lanes closure out of 6 weeks duration
Phase 2
14 nights (nearly 3 weeks) closure, plus 2 weeks 2-way lights, out of 6 weeks duration
Phase 3A
4 nights closure, out of 10 weeks duration
Phase 3A1
4 nights closure, out of 7 weeks duration
Phase 3A2
4 weeks closure northbound including 4 nights total closure, out of 4 weeks duration
Phase 4
2 weeks closure northbound, out of 2 weeks duration
Summary of Total Works
Nearly 26 weeks closures out of 78 to 80 weeks total duration
Burpham Section Summary
London Road closed nearly 9 weeks out of 18 to 20 weeks, plus 4 weeks side road closures (to be confirmed)
Phase 0
4 weeks closure of Burpham Lane and New Inn Lane, will affect Aldi customers significantly.
Phase 1
10 nights total closure out of 4 weeks duration.
Phase 2
4 nights total closure out of 7 to 8 weeks duration
Phase 3
6 weeks northbound closure out of 7 to 8 weeks duration
Boxgrove Roundabout Summary
4- way traffic lights for 4 phases, with no closures, out of 21 weeks duration
Stoke Park/Guildford High School Section Summary
Nearly 17 weeks closure, out of 35 weeks duration
Phase 1
6 weeks total closure, incorporating 4 weeks Nightingale Road and Cross Lanes closure out of 6 weeks duration
Phase 2
14 nights (nearly 3 weeks) closure, plus 2 weeks 2-way lights, out of 6 weeks duration
Phase 3A
4 nights closure, out of 10 weeks duration
Phase 3A1
4 nights closure, out of 7 weeks duration
Phase 3A2
4 weeks closure northbound including 4 nights total closure, out of 4 weeks duration
Phase 4
2 weeks closure northbound, out of 2 weeks duration